WORKDAY vs Calendar Days
Set a deadline a given number of working days out, not calendar days.
What you will learn
- Use WORKDAY to add a number of working days to a start date
- Explain why simply adding the day count to the date counts weekends as if work happened on them
- Recognise that the difference grows with every weekend the span crosses
Excel skills
WORKDAY · Date Calculations
The task
Each task needs a set number of working days to complete. Work out the deadline for each one, in column C - the calendar date that many working days after the start.
You work in a real spreadsheet in your browser, and your answer is checked against hidden traps the moment you submit.